To provide the university community with guidance on initiating
facility projects involving remodeling, renovation, or
construction
All requests for Capital Programs Management Group (CPMG)
estimates and design services for facility remodeling, renovation,
or construction must be approved by the responsible vice president.
The user must prepare the request on a Capital Project Request for Estimate form or
submit the request in writing with the information contained on the
form. Each project estimate request must be signed by the
responsible dean or director.
Requests for CPMG services typically begin with a request for
estimate. Requests are sent to the CPMG through the following
processes:
Responsibility
|
Action
|
| User |
- Identify and define the project request.
- Prepare the Request for Estimate form, noting the
following:
- a description of the service being requested
and
- the name and phone number of the department
representative.
- Submit the request form to the dean or director for review and
approval.
|
| Dean or director |
- Approve or disapprove the request.
|
|
If not approved: |
|
- Indicate “not approved” on the request form and
return it to the user’s department.
|
|
If approved: |
|
- Sign the request form.
- Submit the request form to the appropriate vice president for
review and approval.
|
| Vice president |
- Approve or disapprove the request.
|
|
If not approved: |
|
- Return the request to the dean or director with an explanation
for denial.
|
|
If approved: |
|
- Sign the request form.
- Send a copy of the signed request form to the user’s
department, retain a file copy, and send a copy to the Capital
Programs Management Group (CPMG).
|
| Capital Programs Management Group (CPMG) |
- Log in the request form and assign:
- a project number
and
- a project manager.
- Send an acknowledgment to the user, noting the assigned CPMG
project number and project manager.
|
| CPMG project manager |
- Meet with or contact the user within five working days of the
acknowledgment letter.
|
CPMG project manager
and
CPMG assistant director |
- Meet to determine whether the project requires outside
consultants. (See CPM 311–01,
“Consultants for Remodeling, Renovation, and
Construction—General.”)
|
|
If the project does not require outside consultants for
preliminary program and cost estimates: |
|
- Skip to step 21.
|
|
If it is apparent that the total project cost will be $2
million or more: |
|
- Follow the regents’ procedure (see the Arizona Board of
Regents Web site), as well as the
appropriate CPM 300 section policies
and procedures applicable to major capital
projects.
|
|
If it is apparent that the total project cost will be less than
$2 million and the project requires outside consultants for
preliminary program and cost estimates: |
| CPMG |
- Request proposals from appropriate consultants.
- Review proposals with the user and recommend that the user
obtain funding for the planning phase only.
- Prepare, using outside consultants, preliminary design and
budget estimates.
| Note: |
New construction estimates must be consistent with the Board of
Regents’ Capital Cost Control
Guidelines. |
- Send a preliminary budget estimate memorandum and estimate
documents to the user with a copy to the dean or director for the
approval of user’s org manager and/or vice
president.
|
| User |
- Review the preliminary budget estimate memorandum and estimate
documents. Determine whether the project is
acceptable.
|
|
If not acceptable: |
|
- Notify the CPMG to cancel or postpone the project, or to review
the project for a change in the project scope.
|
|
If acceptable: |
|
- Send the estimate to the org manager.
|
| Org manager |
- Enter the agency/org number to be used for transfer of funds to
the plant fund agency/org, identify the funding source, and sign
the preliminary budget estimate memorandum.
- Submit the preliminary budget estimate memorandum to the
responsible vice provost or vice president for
approval.
|
| Responsible vice provost or vice president |
- Review the preliminary budget estimate memorandum and approve
or disapprove it.
|
|
If disapproved: |
|
- Notify the user to contact the CPMG and cancel or postpone the
project.
|
|
If approved: |
|
- Verify the funding source, sign the preliminary budget estimate
memorandum, send the original to Financial Services, and send a
copy to the user.
|
| Financial Services |
- Establish a project plant fund agency/org with the director of
the CPMG (or designee) as the org manager.
- Complete the Financial Services section of the preliminary
budget estimate memorandum, return the original to the CPMG, and
send copies to the user, the user org manager, and the responsible
vice president.
- Transfer funds from the agency/org identified on the
preliminary budget estimate memorandum to the established plant
fund agency/org.
|
| CPMG |
- Proceed with the project.
|
This policy does not apply to general maintenance and repair
services provided by Facilities Management (FM).
The user may send a Request for Estimate directly to FM if the
user determines or anticipates that:
In this case, it is not necessary to have the responsible vice
president sign the Capital Project Request for Estimate form.