| Schedule (tentative) | ||||||
| Manual Excavation Assumed; 3 Days per foundation | *May vary depending number of Laborers | |||||
| March | ||||||
| Monday 2 | Tuesday 3 | Wednesday 4 | Thursday 5 | Friday 6 | Saturday 7 | Sunday 8 |
| Anchor 1 Excavation / Foundation Layout | Excavation | Excavation | Sunday | |||
| Monday 2 | Tuesday 3 | Wednesday 4 | Thursday 5 | |||
| Anchor 2 Excavation / Foundation Layout | Excavation | Excavation | Construction of Tower Foundation 1 | Construction of Tower Foundation 1 | Construction of Tower Foundation 2 | Sunday |
| Thursday 4 | ||||||
| Construction of Tower Foundation 2 | Finish Whatever is left, material transport and money transfer time may not allow It to start right on time but this is the basic schedule. | |||||
| May | ASU Team | |||||
| Friday 15 | Saturday 16 | Sunday 17 | ||||
| Departure from PHX and Arrival in Honduras | Travel to the Town/ Organize and go over plans | Sunday | ||||
| Monday 18 | Tuesday 19 | Wednesday 20 | Thursday 21 | Friday 22 | Saturday 23 | Sunday 24 |
| Collection of Materials | Collection of Materials & Transportation | Cement Pouring of Anchors | Cement Curing / Prepare Cables and Wood | Cement Curing / Prepare Cables and Wood | Cement Curing / Prepare Cables and Wood | Sunday |
| Monday 25 | Tuesday 26 | Wednesday 27 | Thursday 28 | Friday 29 | Saturday 30 | Sunday 31 |
| Cable Hoisting | Cable Hoisting / Rust Protection for Cable | Walkway Fitting | Walkway Fitting | Seal Wood & Fence Weaving (WWF) | Final Details, Water Management / Clean up !! | Sunday |
| Monday 1 | Tuesday 2 | Wednesday 3 | Thursday 4 | Friday 5 | Saturday 6 | Sunday 7 |
| Departure from Village | Possibly stay a few extra days in case something goes wrong and go sight seeing if finished early. | |||||