Schedule (tentative)
Manual Excavation Assumed; 3 Days per foundation *May vary depending number of Laborers
March
Monday 2 Tuesday 3 Wednesday 4 Thursday 5 Friday 6 Saturday 7 Sunday 8
      Anchor 1 Excavation / Foundation Layout Excavation Excavation Sunday
Monday 2 Tuesday 3 Wednesday 4 Thursday 5      
Anchor 2 Excavation / Foundation Layout Excavation Excavation Construction of Tower Foundation 1 Construction of Tower Foundation 1 Construction of Tower Foundation 2 Sunday
Thursday 4            
Construction of Tower Foundation 2 Finish Whatever is left, material transport and money transfer time may not allow It to start right on time but this is the basic schedule.          
May  ASU Team
Friday 15 Saturday 16 Sunday 17
Departure from PHX and Arrival in Honduras Travel to the Town/ Organize and go over plans Sunday
Monday 18 Tuesday 19 Wednesday 20 Thursday 21 Friday 22 Saturday 23 Sunday 24
Collection of Materials Collection of Materials & Transportation Cement Pouring of Anchors Cement Curing / Prepare Cables and Wood Cement Curing / Prepare Cables and Wood Cement Curing / Prepare Cables and Wood Sunday
Monday 25 Tuesday 26 Wednesday 27 Thursday 28 Friday 29 Saturday 30 Sunday 31
Cable Hoisting Cable Hoisting / Rust Protection for Cable Walkway Fitting Walkway Fitting Seal Wood & Fence Weaving (WWF) Final Details, Water Management / Clean up !! Sunday
Monday 1 Tuesday 2 Wednesday 3 Thursday 4 Friday 5 Saturday 6 Sunday 7
Departure from Village Possibly stay a few extra days in case something goes wrong and go sight seeing if finished early.