Purpose

[horizontal rule]

To fiscally account for each sponsored project according to university, state, and sponsor regulations

[horizontal rule]

Sources

[horizontal rule]
United States. Office of Management and Budget. OMB Circular A-110 (as amended on 9/30/99)
Office for Research and Sponsored Projects Administration
Financial Services

[horizontal rule]

Policy

[horizontal rule]

As required by OMB Circular A-110, a separate agency/org is established within the university financial system for each sponsored project. All budget and financial transactions, including receipts, encumbrances, and expenditures, are reflected in the accounting records for each agency/org. The physical award file is centrally maintained in the Office for Research and Sponsored Projects Administration and is the university’s official administrative record of the project. This central file must contain the documentation authorizing agency/org set up and award acceptance and contain copies of official award administrative actions, technical and financial reports and close out materials. The sponsor’s representatives may examine these files.

[horizontal rule]

ProceduresD

[horizontal rule]


Establishing an Agency/Org with an Award Document


Responsibility
Action
Sponsored projects officer
  1. Review the award documents, attachments, and proposal file to assure that the award is in compliance with appropriate regulations and that technical reporting requirements are acceptable.
  2. Negotiate changes as needed.
  3. Obtain principal investigator’s (PI’s) approval to accept the award.
  4. Discuss with the principal investigator any special limitation and reporting requirements required by the sponsor.
  5. Obtain signature from an authorized official of the university when required.
  6. Obtain agency/org number from Grant and Contract Accounting (GCA) and prepare Sponsored Project Award Notice and associated activation materials.
  7. Forward Sponsored Project Award Notice and supporting materials and proposal to the Office for Research and Sponsored Projects Administration central administration unit for data input and routing to GCA.
Sponsored projects accountant
  1. Review the activation package for completeness and accuracy.
  2. Establish the agency/org in the university financial system.
  3. Send request to Financial Services to establish the principal investigator as agency/org manager.
  4. Send the Sponsored Project Award Notice, copy of the award document, terms and conditions, and other supporting materials to the:
    1. principal investigator(s)
    2. department chair(s)
    3. dean(s)

      and

    4. other designated individuals.
Upon receipt of award notice:
Principal investigator
  1. Review notices and supporting materials. Contact the sponsored projects officer to discuss any special limitations, documentation requirements for deliverables, reporting requirements, and any other items of concern.
  2. Complete necessary authorization forms to establish new agency/org managers and/or authorized signers. Sign the signature cards and return them to Financial Services. (For further information and sample forms, see the Financial Services Policies and Procedures Manual—FIN 202, “Establishment of Agency/Orgs.”)
  3. Initiate payroll actions (where appropriate) for any faculty, staff, or students who will be employed on the project and process all necessary purchasing documents to begin work.

endtable1


Establishing an Agency/Org without an Award Document

A principal investigator may request that an agency/org be established before receipt and/or execution of the official award document when adequate information is available to ensure that an award is forthcoming.

This procedure may be used to incur pre-award costs or to continue existing agency/orgs when funding is incremental or delayed due to the federal budgeting process. A guarantee must be made that any pre-award costs incurred will be covered by a nonsponsored agency/org should the award not be made or if the incurred costs are otherwise unallowable. The guarantee will be required only for direct costs, though applicable facilities & administrative costs will be budgeted at the pre-award stage. D


Responsibility
Action
Principal investigator
  1. Initiate a request for establishment of a sponsored project agency/org by writing a Request to Establish an At-Risk Account Memorandum to the sponsored projects officer assigned to the academic unit.
  2. Obtain the agency/org manager signature for the guarantee agency/org.
  3. Note: This signature guarantees the costs will be covered if:
    1. the award does not come through

      or

    2. the pre-award costs are not allowable under the terms of the award agreement.
If approved:
Sponsored projects officer (SPO)
  1. Review budget request for 301b and departmental guarantee to ensure that the proper authority to set up agency/org exists and that costs are allowable.
  2. Confirm project status with sponsor and document recommendation.
  3. Obtain agency/org number from Grant and Contract Accounting (GCA) and prepare a Sponsored Project Pre-award Notice. Attach appropriate backup and forward to the Office for Research and Sponsored Projects Administration central administration unit for data input and routing to GCA.
Sponsored projects accountant
  1. Establish the agency/org in the university financial system.
  2. Send request to Financial Services to have principal investigator set up as agency/org manager.
  3. Distribute Sponsored Projects Pre-award Notice and supporting materials to:
    1. principal investigator(s)
    2. department chair(s)
    3. dean(s)

      and

    4. other designated individuals.
If denied:
SPO
  1. Return the Request to Establish an At-Risk Account Memorandum to the principal investigator.
  2. Discuss with the principal investigator options available to meet the immediate needs of the project.
endtable2