PUR 402–03
Table |
Procedure for Professional Services if the
Contract Amount is More than $250,000 and for All Construction
Services Obtained in a One-Step Solicitation Using
Construction-Manager-at-Risk, Design-Build, and
Job-Order-Contracting Methods
The Capital Program Management Group (CPMG) submits the
description of the project, scope of work, and the evaluation
criteria for this project to Purchasing and Business Services
(PBS).
PBS prepares a request for statements of qualifications and
experience (RFQ) for the specific design and/or construction
services needed on the project.
CPMG:
- submits a Payment Voucher (PV) to PBS for advertising the RFQ
for the project
and
- nominates an evaluation committee on an Evaluation Committee Selection Authorization
form. This form is submitted to the director of PBS. If the RFQ is
for professional services, the director of PBS will determine the
number and qualifications of the evaluation committee members. If
the RFQ is for construction services, the evaluation committee will
not have more than seven members and must include one person who is
an outside licensed contractor and one person who is a registered
architect or engineer. These licensed and registered people may be
employees of the university or outside consultants. If outside
consultants, they will not be compensated for providing this
service, but may be reimbursed reasonable expenses. These licensed
and registered people may not provide and may not be affiliated
with a firm that provides any goods or services relating to the
project covered by the RFQ.
PBS:
- advertises the RFQ in accordance with PUR 501–02, “Advertising for
Bids”
- mails or otherwise distributes the RFQ to a wide number of
professional and/or construction services firms, including small
and disadvantaged firms
- receives and logs responses to the RFQ
- rejects any received after the date and time set for closing
the RFQ
and
- after the RFQ is closed, forwards responses to the evaluation
committee.
The evaluation committee:
- evaluates the statements of qualifications and experience
submitted in response to the RFQ
- conducts discussions with at least three but not more than five
persons or firms as specified in the RFQ regarding the contract and
the relative methods of approach for furnishing the required
professional or construction services
- in order of preference, based on criteria established and
published in the RFQ, selects a short list of three of the persons
or firms the evaluation committee deems to be the most qualified to
provide the professional or construction services. The selection of
the short list and order of preference must be based on
demonstrated competence and qualifications only. Fees, price,
man-hours, or any other cost information may not be requested or
considered in the selection of the short list or order of
preference. For an RFQ for construction services only, the short
list does not include any person or firm that includes or employs
any person or firm that has provided for compensation any services
relating to the project covered by the RFQ. If only two responsible
and responsive persons or firms respond to the solicitation, the
evaluation committee may either proceed with the selection process
with those two persons or firms or request that PBS readvertise the
RFQ
and
- submits the short list in order of preference through the
assistant vice provost and facilities chief planning officer to the
director of PBS.
The director of PBS or designee:
- issues a notice of intent to award a contract for professional
or construction services to one of the persons or firms on the
short list prepared by the evaluation committee. If only two
persons or firms are on the short list, the director of PBS or
designee may elect either to proceed with the selection process or
to readvertise the RFQ
- enters into negotiations for a contract with the person or firm
most qualified to provide the professional or construction
services. The director of PBS or designee takes into consideration
compensation and other contract terms that are determined to be
fair and reasonable to the university. In making this decision, the
estimated value, scope, complexity, and nature of the professional
or construction services to be rendered are taken into account. If
unable to negotiate a satisfactory contract with the person or firm
considered to be the most qualified, the director of PBS or
designee formally terminates negotiations with that person or firm
and undertakes negotiations with the next most qualified person or
firm in sequence until an agreement is reached or a determination
is made to reject all persons or firms on the short list. If a
contract for construction services is entered into, construction
shall not commence until the university and contractor agree in
writing on a fixed price or a guaranteed maximum price for the
construction to be commenced
- provides a memorandum to CPMG outlining the fee negotiations
and the final proposed fee for service
and
- files a copy in the contract file.
CPMG forwards to PBS a Purchase Request for the required
services and any information needed to complete the contract
documents.
PBS:
- prepares the contract documents in three originals and obtains
appropriate signatures
- monitors the process to ensure that documents and any required
insurance certificates and bonds are returned in a timely
manner
- distributes an original of the contract documents to PBS, to
the contractor, and to the design professional
and
- issues a Purchase Order to encumber funds and accommodate the
billing and payment process.
When the project is complete, CPMG submits to PBS all project
closeout data and documentation, including the Consultant
Performance Evaluation form as applicable.
Procedure for Construction Services Obtained
in a Two-Step Solicitation Using Design-Build and
Job-Order-Contracting Methods
All steps in the preceding procedure are followed through the
submission of the short list by the evaluation committee to the
director of PBS.
The director of PBS or designee:
- issues a request for proposals (RFP) to the persons or firms on
the short list developed pursuant to the preceding steps
- includes the following in the RFP:
- the university’s schedule and budget for the project or a
life-cycle budget if the procurement includes maintenance or
operations services
- a statement that the contract will be awarded to the person or
firm whose proposal receives the highest number of points under a
scoring method
- a description of the scoring methods, including the factors
used and the number of points allocated to each:
Required Scoring Factors
- demonstrated compliance with design requirements (for
design-build construction services only)
- offeror qualifications
- offeror financial capacity
- compliance with the university’s project schedule
- for design-build construction services only, if the RFP
specifies that the university will spend its project budget and not
more than its project budget and is seeking the best proposal for
the project budget, compliance of the offeror’s price with
the university’s project budget
- price for job-order-contracting construction services or price
for design-build construction services or life-cycle price for
procurements that include maintenance, operations, or finance
services, if the RFP does not include the budget specifications in
item 5 above
- offeror quality management plan
and
- any other evaluation factors determined by the
university.
- design requirements (for design-build construction services
only)
- the requirement for separate submissions of technical proposal
and price proposal, which together are responsive to the
requirements in the RFP. For design-build construction services,
the price proposal is a fixed or a guaranteed maximum price
- a statement that the selection committee evaluates and scores
the technical proposal separately and before opening and evaluating
the price proposal
- a statement that, if the university conducts discussions
pursuant to step 3 (following), each offeror must submit a
preliminary technical proposal before the discussions are held
and
- for design-build construction services only, the percentage to
be used in calculating the stipulated fee mentioned
below.
and
- if determined by the university and included in the RFP,
conducts discussions with all persons or firms that submit
preliminary technical proposals to ensure full understanding of,
and responsiveness to, the solicitation requirements
- accords fair treatment with respect to any opportunity for
discussion and for clarification by the offeror
- permits revision of preliminary technical proposals before
award for the purpose of obtaining the best and final proposals
and
- does not disclose information derived from proposals submitted
by competing offerors during any discussions with
offerors.
PBS:
- after completion of any discussions pursuant to the preceding
step or if no discussions are held, requests each offeror to submit
separately its final technical proposal and its sealed price
proposal to PBS
and
- forwards the final technical proposals to the evaluation
committee and holds the sealed price proposals unopened.
The evaluation committee opens, evaluates, and scores the final
technical proposals using the scoring method in the RFP before
receiving any price proposal. No other factors or criteria may be
used in the evaluation and scoring.
After completion of the evaluation and scoring of all final
technical proposals, PBS delivers sealed price proposals to the
evaluation committee.
The evaluation committee:
- opens, evaluates, and scores the price proposals and completes
the scoring of the entire proposal using the scoring method in the
RFP. No other factors or criteria may be used in the evaluation and
scoring
and
- forwards to PBS a signed memorandum documenting the scoring for
all final technical and price proposals and makes a recommendation
for award.
The director of PBS or designee:
- awards the contract to the responsive and responsible offeror
whose proposal receives the highest score under the method of
scoring in the RFP. No other factors or criteria may be used in the
evaluation
- files the basis on which the award was made in the contract
file
and
- for design-build construction services only, awards a
stipulated fee equal to a percentage, as prescribed in the RFP, of
the university’s project budget, but not less than
two-tenths of one percent of the project budget to each short
list offeror who provides a responsive, but unsuccessful, proposal.
If a contract is not awarded, all responsive short list offerors
receive the stipulated fee. The stipulated fee is paid to each
offeror within 90 days after the award of the initial contract or
the decision not to award a contract.
Note: In consideration for paying the stipulated fee, the
director of PBS or designee may use any ideas or information
contained in the proposals in connection with any contract awarded
for the project, or in connection with a subsequent procurement,
without any obligation to pay any additional compensation to the
unsuccessful offerors. Notwithstanding the other provisions of this
paragraph, an unsuccessful short list offeror may elect to waive
the stipulated fee. If an unsuccessful short list offeror elects to
waive the stipulated fee, the university may not use ideas and
information contained in the offeror’s proposal. However,
this restriction does not prevent the university from using any
idea or information included in a proposal of an offeror that
accepts the stipulated fee.
CPMG forwards to PBS a Purchase Request for the required
services and any information needed to complete the contract
documents.
PBS:
- prepares the contract documents in three originals and obtains
appropriate signatures
- monitors the process to ensure that the documents and any
required insurance certificates and bonds are returned in a timely
manner
- distributes an original of the contract documents to PBS, to
the contractor, and to CPMG for any other consultants or
contractors
and
- issues a Purchase Order to encumber funds and accommodate the
billing and payment process.
When the project is complete, CPMG submits to PBS all project
closeout data and documentation, including the Consultant
Performance Evaluation form as applicable.
Procedure for Any Solicitation Conducted per
the Foregoing Procedures
All parties have the following responsibilities:
- until award and execution of a contract by a university, make
only the name of each person or firm on any short list available to
the public. Keep all other information received by the university
in response to a request for qualifications (RFQ) or a request for
proposals (RFP) confidential to avoid disclosure of the contents
that may be prejudicial to competing offerors during the selection
process
- open proposals to public inspection after the contract is
awarded and the university has executed the contract
- to the extent that an offeror designates and the university
concurs, trade secrets and other proprietary data contained in a
proposal remain confidential
and
- refer any request for information relating to a proposal
resulting from an RFQ or RFP under evaluation to Purchasing and
Business Services (PBS).
The director of PBS or designee may cancel an RFQ or RFP or
reject in whole or in part any or all proposals as specified in the
solicitation if it is in the best interest of the university; the
reasons for cancellation or rejection become part of the contract
file.
Return to PUR
402–03