PUR 402–03:
Professional Design Services Costing More than $250,000 and
Construction Services |
![[horizontal rule]](purhr.gif)
Purpose
![[horizontal rule]](purhr.gif)
To allocate responsibilities for the steps in selecting
professional design services costing more than $250,000 and for
obtaining construction services (the Arizona Board of Regents
Policy Manual specifies legal requirements that are not fully
covered in this procedure)
![[horizontal rule]](purhr.gif)
Sources
![[horizontal rule]](purhr.gif)
Arizona Board of Regents Policy Manual -
3-804
University policy
![[horizontal rule]](purhr.gif)
Applicability
![[horizontal rule]](purhr.gif)
Design and construction consultants and
contractors
![[horizontal rule]](purhr.gif)
Policy
![[horizontal rule]](purhr.gif)
The university may procure design services, construction, and
construction services, as applicable, under any of the following
project delivery methods:
- design-bid-build
- construction-manager-at-risk
- design-build
and
- job-order-contracting.
![[horizontal rule]](purhr.gif)
ProceduresD
![[horizontal rule]](purhr.gif)
Procedure for Professional Services if the
Contract Amount is More than $250,000 and for All Construction
Services Obtained in a One-Step Solicitation Using
“Construction-Manager-at-Risk,” “Design-Build,” and
“Job-Order-Contracting” Methods
Responsibility
|
Action
|
| Capital Programs Management Group (CPMG) |
- Submit the description of the project, scope of work,
and the evaluation criteria for this project to Purchasing and
Business Services (PBS).
|
| Purchasing and Business Services (PBS) |
- Prepare a request for statements of qualifications
and experience (RFQ) for the specific design and/or construction
services needed on the project.
|
| CPMG |
- Submit a Payment Voucher (PV) to PBS for advertising
the RFQ for the project.
- Nominate an evaluation committee on an Evaluation Committee Selection Authorization
form. This form is submitted to the director of PBS. If the RFQ is
for professional services, the director of PBS will determine the
number and qualifications of the evaluation committee members. If
the RFQ is for construction services, the evaluation committee will
not have more than seven members and must include one person who is
an outside licensed contractor and one person who is a registered
architect or engineer. These licensed and registered people may be
employees of the university or outside consultants. If outside
consultants, they will not be compensated for providing this
service, but may be reimbursed reasonable expenses. These licensed
and registered people may not provide and may not be affiliated
with a firm that provides any goods or services relating to the
project covered by the RFQ.
|
| PBS |
- Advertise the RFQ in accordance with PUR 501–02, “Advertising for
Bids.”
- Mail or otherwise distribute the RFQ to a wide number of
professional and/or construction services firms, including small
and disadvantaged firms.
- Receive and log responses to the RFQ. Reject any received after
the date and time set for closing the RFQ. After the RFQ is closed,
forward responses to the evaluation committee.
|
| Evaluation Committee |
- Evaluate the statements of qualifications and
experience submitted in response to the RFQ.
- Conduct discussions with at least three but not more than five
persons or firms as specified in the RFQ regarding the contract and
the relative methods of approach for furnishing the required
professional or construction services.
- In order of preference, based on criteria established and
published in the RFQ, select a short list of three of the persons,
or firms, the evaluation committee deems to be the most qualified to
provide the professional or construction services. The selection of
the short list and order of preference must be based on
demonstrated competence and qualifications only. Fees, price,
man-hours, or any other cost information may not be requested or
considered in the selection of the short list or order of
preference. For an RFQ for construction services only, do not
include on the short list any person or firm that includes or
employs any person or firm that has provided for compensation any
services relating to the project covered by the RFQ. If only two
responsible and responsive persons or firms respond to the
solicitation, the evaluation committee may either proceed with the
selection process with those two persons or firms or request that
PBS readvertise the RFQ.
- Submit the short list in order of preference through the
assistant vice provost and facilities chief planning officer to the
director of PBS.
|
| Director of PBS or designee |
- Issue a notice of intent to award a contract for professional
or construction services to one of the persons or firms on the
short list prepared by the evaluation committee. If only two
persons or firms are on the short list, the director of PBS or
designee may elect either to proceed with the selection process or
to readvertise the RFQ.
- Enter into negotiations for a contract with the person or firm
most qualified to provide the professional or construction
services. Include consideration of compensation and other contract
terms that are determined to be fair and reasonable to the
university. In making this decision, take into account the
estimated value, scope, complexity, and nature of the professional
or construction services to be rendered. If unable to negotiate a
satisfactory contract with the person or firm considered to be the
most qualified, formally terminate negotiations with that person or
firm and undertake negotiations with the next most qualified person
or firm in sequence until an agreement is reached or a
determination is made to reject all persons or firms on the short
list. If a contract for construction services is entered into,
construction shall not commence until the university and contractor
agree in writing on a fixed price or a guaranteed maximum price for
the construction to be commenced.
- Provide a memorandum to CPMG outlining the fee negotiations and
the final proposed fee for service. File a copy in the contract
file.
|
| CPMG |
- Forward to PBS a Purchase Request for the required
services and any information needed to complete the contract
documents.
|
| PBS |
- Prepare the contract documents in three originals
and obtain appropriate signatures. Monitor the process to ensure
that documents and any required insurance certificates and bonds
are returned in a timely manner.
- Distribute an original of the contract documents to PBS, to the
contractor, and to the design professional.
- Issue a Purchase Order to encumber funds and accommodate the
billing and payment process.
|
| CPMG |
- When the project is complete, submit to PBS all
project close-out data and documentation, including the Consultant
Performance Evaluation form as
applicable.
|
Procedure for Construction Services Obtained in
a Two-Step Solicitation Using “Design-Build” and
“Job-Order-Contracting” Methods
Responsibility
|
Action
|
| |
Steps 1 through 11 are the same as the preceding
procedure. |
| Director of PBS or designee |
- Issue a request for proposals (RFP) to the persons
or firms on the short list developed pursuant to the preceding
steps.
- Include the following in the RFP:
- the university’s schedule and budget for the project or a
life-cycle budget if the procurement includes maintenance or
operations services
- a statement that the contract will be awarded to the person or
firm whose proposal receives the highest number of points under a
scoring method
- a description of the scoring methods, including the factors
used and the number of points allocated to each.
Required Scoring Factors
- demonstrated compliance with design requirements (for
design-build construction services only)
- offeror qualifications
- offeror financial capacity
- compliance with the university’s project schedule
- for design-build construction services only, if the RFP
specifies that the university will spend its project budget and not
more than its project budget and is seeking the best proposal for
the project budget, compliance of the offeror’s price with
the university’s project budget
- price for job-order-contracting construction services or price
for design-build construction services or life-cycle price for
procurements that include maintenance, operations, or finance
services, if the RFP does not include the budget specifications in
item 5 above
- offeror quality management plan
and
- any other evaluation factors determined by the
university.
- design requirements (for design-build construction services
only)
- the requirement for separate submissions of technical proposal
and price proposal, which together are responsive to the
requirements in the RFP. For design-build construction services,
the price proposal is a fixed or a guaranteed maximum price
- a statement that the selection committee evaluates and scores
the technical proposal separately and before opening and evaluating
the price proposal
- a statement that, if the university conducts discussions
pursuant to step 14 (following), each offeror must submit a
preliminary technical proposal before the discussions are held
and
- for design-build construction services only, the percentage to
be used in calculating the stipulated fee under step 23
below.
- If determined by the university and included in the RFP,
conduct discussions with all persons or firms that submit
preliminary technical proposals to ensure full understanding of,
and responsiveness to, the solicitation requirements. Accord fair
treatment with respect to any opportunity for discussion and for
clarification by the offeror. Permit revision of preliminary
technical proposals before award for the purpose of obtaining the
best and final proposals. Do not disclose information derived from
proposals submitted by competing offerors during any discussions
with offerors.
|
| PBS |
- After completion of any discussions pursuant to step
14 (preceding) or if no discussions are held, request each offeror
to submit separately its final technical proposal and its sealed
price proposal to PBS.
- Forward the final technical proposals to the evaluation
committee and hold the sealed price proposals
unopened.
|
| Evaluation Committee |
- Open, evaluate, and score the final technical
proposals using the scoring method in the RFP before receiving any
price proposal. No other factors or criteria may be used in the
evaluation and scoring.
|
| PBS |
- After completion of the evaluation and scoring of
all final technical proposals, deliver sealed price proposals to
the evaluation committee.
|
| Evaluation Committee |
- Open, evaluate, and score the price proposals and
complete the scoring of the entire proposal using the scoring
method in the RFP. No other factors or criteria may be used in the
evaluation and scoring.
- Forward to PBS a signed memorandum documenting the scoring for
all final technical and price proposals and make a recommendation
for award.
|
| Director of PBS or designee |
- Award the contract to the responsive and responsible
offeror whose proposal receives the highest score under the method
of scoring in the RFP. No other factors or criteria may be used in
the evaluation.
- File the basis on which the award was made in the contract
file.
- For design-build construction services only, award a
stipulated fee equal to a percentage, as prescribed in the RFP, of
the university’s project budget, but not less than
two-tenths of one percent of the project budget to each short
list offeror who provides a responsive, but unsuccessful, proposal.
If a contract is not awarded, all responsive short-list offerors
receive the stipulated fee. Pay the stipulated fee to each offeror
within 90 days after the award of the initial contract or the
decision not to award a contract.
| Note: |
In consideration for paying the stipulated fee, the director of
PBS or designee may use any ideas or information contained in the
proposals in connection with any contract awarded for the project,
or in connection with a subsequent procurement, without any
obligation to pay any additional compensation to the unsuccessful
offerors. Notwithstanding the other provisions of this paragraph,
an unsuccessful short-list offeror may elect to waive the
stipulated fee. If an unsuccessful short-list offeror elects to
waive the stipulated fee, the university may not use ideas and
information contained in the offeror’s proposal. However,
this restriction does not prevent the university from using any
idea or information included in a proposal of an offeror that
accepts the stipulated fee. |
|
| CPMG |
- Forward to PBS a Purchase Request for the required
services and any information needed to complete the contract
documents.
|
| PBS |
- Prepare the contract documents in three originals
and obtain appropriate signatures. Monitor the process to ensure
that the documents and any required insurance certificates and
bonds are returned in a timely manner.
- Distribute an original of the contract documents to PBS, to the
contractor, and to CPMG for any other consultants or
contractors.
- Issue a Purchase Order to encumber funds and accommodate the
billing and payment process.
|
| CPMG |
- When the project is complete, submit to PBS all
project close-out data and documentation, including the Consultant
Performance Evaluation form as
applicable.
|
Procedure for Any Solicitation Conducted per the
Foregoing Procedures
Responsibility
|
Action
|
| All parties |
- Until award and execution of a contract by a
university, make only the name of each person or firm on any short
list available to the public. Keep all other information received
by the university in response to a request for qualifications (RFQ)
or a request for proposals (RFP) confidential to avoid disclosure
of the contents that may be prejudicial to competing offerors
during the selection process. Open proposals to public inspection
after the contract is awarded and the university has executed the
contract. To the extent that an offeror designates and the
university concurs, trade secrets and other proprietary data
contained in a proposal remain confidential. Refer any request for
information relating to a proposal resulting from an RFQ or RFP
under evaluation to Purchasing and Business
Services.
|
Director of Purchasing and
Business Services or designee |
- Cancel an RFQ or RFP or reject in whole or in part
any or all proposals as specified in the solicitation if it is in
the best interest of the university. Make the reasons for
cancellation or rejection part of the contract
file.
|
endtable
![[horizontal rule]](purhr.gif)
Cross-References
![[horizontal rule]](purhr.gif)
For information on the procurement of personal/professional
services for purposes other than construction projects, see
PUR 402–01,
“Personal/Professional Services.”
For information on the procurement of design and construction
consultant services costing less than $250,000 and for construction
projects, see PUR 402–02,
“ Professional Design Services Costing $250,000 or Less.”
For information on contract forms for professional services, see
PUR 504–02, “Contract
Forms.”
For additional information on the procurement of services,
see:
- the Financial Services Policies and Procedures
Manual—FIN
421–01, “Guest Lecturers, Consultants, and Other
Independent Contractors”
- the Research and Sponsored Projects Policies and Procedures
Manual—RSP
503–03, “Consultants, Lecturers, and Other
Professional Services for Sponsored Projects”
and
- the Staff Personnel Policies and Procedures
Manual—SPP
210, “Consultants/Independent
Contractors.”